A garden office is powered by a new circuit run from your house, usually in buried armoured cable, ending at its own small consumer unit (fuse board) in the building. That circuit counts as notifiable work under the Building Regulations, so it should be done by a registered electrician who tests it and hands you the certificates. We install and test electrics across Dorset, Hampshire and Devon, and this guide sets out what the job involves so you can brief it properly and recognise a sound quote. The same principles apply to a shed or workshop.

Smarthometechnical
Plan Safe Garden Office Electrics
Smarthometechnical installs electrical systems across Dorset, Hampshire and Devon, including renewable energy and EV charging.

Visit

TL;DR

Table of Contents

How power gets from the house to the garden office

The most common method is a cable run underground from the property to the outbuilding, though overground and overhead routes exist. According to NICEIC’s guide to wiring a shed, the electrician connects the supply to the house consumer unit or a switched fused connection unit, and fits a small dedicated consumer unit inside the outbuilding where the demand is higher. The same guide says SWA cable is generally used because it is heavy-duty, weather-resistant and designed for burial.

That last point matters for safety as well as durability. Under BS 7671, the wiring standard for the UK, a buried cable needs earthed armour or a metal sheath that can act as a protective conductor, or equivalent duct protection. It also has to be buried deep enough to avoid likely ground disturbance and marked with cable covers or tape, as Elec-Mate’s outbuilding supply guide sets out. In practice the armour is connected to earth at both ends, which is one of the things that gets tested at the end.

Work out the load before anyone digs

The cable, the breaker and the consumer unit all follow from what you plan to run in the building. Walk through the room with a pen:

  1. Lighting. Usually small. LED lighting barely registers.
  2. Sockets. A desk setup, monitors, a printer and a kettle add up faster than people expect. Place sockets where the furniture will go, not where the builder’s drawing suggests.
  3. Heating. This is the big one. An electric heater can draw 2kW to 3kW on its own, according to Meteor Electrical’s shed guide, which also suggests a garden office with a heater usually needs a 32A supply or more, via an SWA cable to a consumer unit.
  4. Future use. Air conditioning, an e-bike charger or a hot tub nearby all change the answer. Decide now, because digging a second trench costs more than sizing the first one generously.

A lightly used storage shed with a light and a couple of sockets can be served by a 16A or 20A circuit from the house board. A garden office with a heater, computers and a kettle is a different job.

Cable size and the length of the run

Cable size is not a guess. Elec-Mate’s garden office guide recommends 3-core SWA with common sizes of 4.0mm² for light loads and short runs, 6.0mm² for medium loads or longer runs, and 10.0mm² for heavy loads or runs over 30 metres.

The reason distance matters is voltage drop. Meteor Electrical explains that BS 7671 allows a 5% drop on power circuits, around 11.5V on a 230V supply, measured from the start of the installation, so the house wiring counts too. For a building about 30m away, it says 4mm² is a common choice for a 20A load and a 32A office supply at that distance usually needs 6mm². Longer runs need 10mm² or more.

To put that into a worked example: a garden office 25m from the back of a Poole semi, with a small heater, a computer and lights, will sit in the 6mm² bracket. The same office at the bottom of a long Devon garden at 40m is a 10mm² conversation. Your electrician should calculate it for your actual route, not quote a standard price per metre.

SWA cable sizes compared with run lengths and loads

Route, depth and what you hit on the way

The shortest line is not always the right one. Avoid tree roots and drainage runs, and think about where you might dig in future, for example a vegetable bed or a new patio.

Depth figures vary in the trade, so it helps to know where they come from. Elec-Mate’s guide specifies a trench at least 500mm deep with a 50mm sand bed and warning tape at half depth, and notes that 0.5m is the figure most UK contractors work to in domestic gardens. Meteor Electrical gives about 450mm under lawns and flower beds, 600mm or more in cultivated ground, and ducting under drives and paths. Treat these as typical, and let your electrician decide on the day once they see the ground. Hampshire chalk, Dorset clay and Devon’s stony, root-filled soil can each change how the trench is dug and what protection goes in it.

What the regulations require

RCD protection and weatherproofing

BS 7671 requires 30mA RCD protection (a device that cuts the power in milliseconds if current leaks, for example through a person) on socket-outlets up to 32A and on domestic circuits supplying lighting, as Elec-Mate’s guide sets out. NICEIC’s garden electrics guide adds that all outdoor sockets should be RCD-protected and weatherproof, most carrying an IP66 rating, and outdoor light fittings should be rated IP44 or higher.

Inside the office, a typical arrangement is its own consumer unit with local isolation, a protective device per circuit, 30mA RCD protection and spare ways. Elec-Mate lists a 6A lighting circuit, a 32A socket circuit and a 16A or 20A dedicated heating circuit as typical. Spare ways are cheap at installation and awkward to add later.

Part P of the Building Regulations covers electrical safety in homes in England and Wales. The IET confirms that it applies to outbuildings such as detached garages, sheds and greenhouses as well as garden lighting around a dwelling. Dorset, Hampshire and Devon are all in England, so it applies to you.

NICEIC states that a new circuit from a house to an outbuilding is notifiable work. It must either be notified to Local Authority Building Control or be completed by an electrician registered on a competent person scheme. According to Elec-Mate, that applies regardless of whether the garden office needed planning permission, and the building control route typically costs £250 to £500 in fees. Registered electricians self-certify and issue the completion certificate themselves.

One clarification from Certio’s Part P guide: Part P is not a licence. Anyone may legally do electrical work in a dwelling if it complies and is notified where required. In practice, though, an unregistered route means paying for building control inspection, and it still has to meet BS 7671. Part P also covers only part of the picture, as the cable, protection and testing all have to be right whatever the paperwork says.

Part P: the legal bit that catches people out

Is it a DIY job?

NICEIC’s view is that it is not: running power to a shed involves complex outdoor and underground wiring, and it recommends a registered electrician. It also advises against using an extension lead as a permanent alternative to wiring the building properly. Leads laid across a lawn or through a window are exposed to weather, mowers and damage, and are not designed for a permanent heater load.

Testing and certificates: what you should receive

When the work is finished, the installation must be inspected and tested. Wales’s official Part P guidance, published on gov.wales, describes the tests that back an installation certificate: continuity, insulation resistance, polarity, earthing, earth fault loop impedance and protective device operation. The principle is the same in England. Elec-Mate’s guide adds that the SWA armour is checked end to end and that RCDs are trip-tested.

You should end up with two documents, according to Certio:

Keep both. A buyer’s solicitor may ask for them when you sell, and an insurer may ask for them after a claim. If the garden office is rented out or used for a business, the wider electrical testing picture changes, and our guide for landlords on EICR deadlines explains how periodic inspection works.

Keeping up with the standard

BS 7671:2018 has been amended several times. Amendment 3 was published on 31 July 2024 and took effect immediately, adding a new regulation (530.3.201) on selecting and erecting protective devices, according to the IET’s official document. A later Amendment 4 is dated 2026. You do not need to know the detail. What it means is that a quote should name BS 7671 and your electrician should be working to the current version.

What a good quote for garden office electrics includes

Compare quotes on content, not only on price. A sound one will set out:

If you are also adding solar, a battery or an EV charger, tell the electrician at the start. A single design is cleaner than three separate trenches and boards. Our article on solar-ready consumer units shows how the house board is prepared for that, and the EV charger installation page covers charging points on the same property.

Perspective

Most of the problems we are asked about on outbuildings are not about the office. They are about the cable between the house and the office: undersized for the heater someone added later, buried shallow because the trench was dug on a weekend, or never certified because nobody realised it was notifiable.

Our view is simple. Treat the supply as permanent infrastructure and size it for what you might plug in within the next ten years, not for what is on the desk today. Plan it alongside any solar, battery or EV charger work so the house consumer unit, the armoured cable and the testing are designed together.

We are electrical contractors, and we highlight our MCS and NICEIC accreditation because certification is exactly what the garden office job turns on. The point of registration is that the work is tested, certified and in your hands when you finish. That is how you want to find it when you sell the house.

Simon

Getting the work done in Dorset, Hampshire and Devon

We are an electrical contractor covering Dorset, Hampshire and Devon, doing residential and commercial work that includes general electrical installation, electrical testing, EV chargers, solar PV and battery storage, and home automation controls. For a garden office, we can look at the house board, the route and the load, and quote the supply and testing. If you want lighting, heating or building controls to be managed from your phone, our home automation service can be included in the same plan.

Smarthometechnical

To discuss a garden office, shed or workshop supply, get in touch through Smart Home Technical. Tell us the length of the route, what you plan to run and whether you are adding anything else to the property.

FAQ

Do I need an electrician to wire a garden office?

Yes. NICEIC says running power to an outbuilding is complex outdoor and underground work and recommends a registered electrician. The new circuit is also notifiable under Part P, which a registered electrician can handle by certifying the work themselves.

What cable do I need for a garden office?

Usually 3-core SWA cable, sized for the load and the length of the run. Typical sizes are 4mm² for light loads over short runs, 6mm² for medium loads or longer runs and 10mm² for heavy loads or runs beyond about 30 metres. Your electrician should calculate the voltage drop for your route.

How deep does the cable need to be buried?

BS 7671 requires a depth that avoids foreseeable ground disturbance, with cable covers or marker tape. In domestic gardens 0.5m is the figure most contractors work to, with deeper burial or ducting under drives and cultivated ground. Your electrician will set the depth for your garden.

What certificate should I get after the work?

An Electrical Installation Certificate for the new circuit, plus a Building Regulations compliance certificate for notifiable work. Keep both with your property records.

Does the same apply to a shed?

Yes. Part P covers sheds, greenhouses and detached garages supplied from a dwelling, so a shed with a light and sockets needs the same safe cable, RCD protection and certification. Only the load, and so the cable size, is usually smaller.

Sources